Fontaine was selected to work with UMass Chan Medical
School to rebrand all signage on campus. This project consisted of the removal
of 14 existing signs, 7 of which were permanently removed. Associated facades
were repaired to match the existing with custom Mirocotta composite panels to
match terracotta, stone patching, building power washing and painting. The
project also included custom design & fabrication and installation of 18
new signs at seven buildings. Fontaine installed a special swing stagging in
excess of 130 feet from grade along with many crane and rigging mobilizations.
This project was successfully constructed and completed on a 24/7 active
hospital and school campus.